Stradins Hospital announced the termination of the contract to the builder on Tuesday, and the contract was terminated unilaterally.
The hospital Council has indicated that the LLC “Velve” is unable to fulfil the obligations laid down in the contract – the time periods for construction are not observed, significant defects have been detected in the construction object which are not rectified, employment of non-harmonized subcontractors has taken place, as well as other violations have been recorded.
The construction contract, signed in August 2020, will be terminated on Tuesday, February 13. The hospital is due to take over the building site on February 20.