New Latvia-Estonia power line completed

Take note – story published 3 years ago

Construction work on the 330 kilovolts (kV) power line from Estonia to Riga TEC-2 in Latvia has been completed, and the power line has been switched on, Latvian transmission operator Augstsprieguma tīkls said December 21.

The power line is scheduled to be commissioned by the middle of next year, but from January 1 the line will be taken into account when calculating the transmission capacity allocated to the electricity market.

Chairman of the Augstsprieguma tīkls board Varis Boks said that the completion of the project is an important step in strengthening the energy independence of Latvia and the Baltic on the way to synchronization of electricity networks with Europe in 2025. 

The new line transmission capacity is 600 MW, which complements the current cross-sectional transmission capacity of Estonia – Latvia. Until now, it was not sufficient to ensure the required volume of electricity trading between Latvia and Estonia, resulting in congestion and differences in electricity prices in certain hours.

Transmission capacity deficit in the Estonian-Latvian cross-section is expected to be eliminated by 2024, when the Valmiera-Tartu and Valmiera-Tsirgulin line reconstruction is finished. The project “Estonia – Latvia's third 330 kV interconnection” is also important for security of energy supply and for sustained functioning of the electricity network, both in Latvia and in the Baltic as a whole.

 

Seen a mistake?

Select text and press Ctrl+Enter to send a suggested correction to the editor

Select text and press Report a mistake to send a suggested correction to the editor

Related articles

More

Most important